SaskTel servicing guidelines
for
existing Multi-Dwelling
Units
3.2. Pathways/Conduit throughout the MDU
“Pathway Creation” in the typical form of conduit routes is the responsibility of the builder.
“Pathways” or conduit is required between all telephone rooms where SaskTel Fibre Optic
Network equipment will be located and the telephone rooms, either main or secondary, and to
the multimedia panel in the individual suite.
With any conduit that is not filled with cable, a labelled rope or pull-string is to be inserted and
secured to prevent its accidental removal.
3.2.1 Riser
In the situation of stacked telephone rooms, sleeve conduit or slots against the running wall
shall be placed for access between these riser communication room/closets. Sleeves need to
be 6” x10” with a curb of 1” or conduit of 4” with a curb of 1-3”.
3.2.2 Horizontal
Conduit is typically 25 mm [1"] EMT, or rigid PVC conduit (per building codes) to the suite wall
box or media panel in each individual unit from floor telephone room. Flexible ENT can be
considered so long as it meets all applicable codes and does not introduce more than 2 -90
degree bends between pull boxes. Depending on building structure, the conduit may be placed
horizontally and/or vertically.
Conduit fill is determined by adding together the cross-sectional areas of all cables to be
installed in a conduit. This total cable area is then compared with the cross-sectional area
available in the conduit.
A traditional rule of thumb is to follow the NEC which specifies that for three or more cables in a
conduit, the total cross-sectional area of the cables must not exceed 40% of the available area
in the conduit. For one or two conductors in a conduit, the maximums are 53% and 31%,
respectively. Determining the maximum allowable conduit fill for a specific installation requires
either reference to a table or a mathematical calculation.
If fibre runs are installed in a multi-drop or multi-point system, where one larger conduit feeds off
to successive units vs. having individual home run conduit, then the conduit at the beginning of
the run should be of a larger diameter to accommodate the multiple single cables to each suite.
The conduit sizing should conform to the following chart.
This table provides a guide for conduit sizing when there are multiple cable in the conduit and is
as per ANSI/TIA 569-B & 570-B.
Kommentare zu diesen Handbüchern